Cuban well progressing slowly

Progress: the Scarabeo 9 is expected to wrap up drilling by mid-May according to reports

Drilling of the first well in the long-awaited exploration of Cuba's offshore oilfields has gone slower than expected, but should be completed by mid-May, according to reports.

Reuters quoted sources close to the project as saying drillers had encountered harder rock beneath the sea bed than expected, which combined with other minor problems, had slowed progress.

When drilling began on 1 February Spanish oil giant Repsol YPF said drilling of the deep-water well was anticipated to take about 60 days to complete.

A Repsol spokesman could not confirm on Friday the projected mid-May completion date, when contacted by Reuters.

This well, which is in 1706 metres of water off the communist-run island's north-west coast, is the first of five currently planned,…