El Bibane partners ready for the big day



By Upstream staff 

The EL Bibane development, off Tunisia, is set to come on stream next month, project partner PA Resources said.

The Swedish player said that operator Candax Energy has completed the installation of the offshore production platform and the tie-in to the oil and gas export pipeline at the EBB-4 well.

Candax added that the pressure has been successfully tested and certified for production operational start up.

However, the EBB-4 well will not be brought on line until completion of the three-well drilling programme and the installation of the gas recycling system.

In a release Sweden's PA said it had been informed by Candax that a considerable volume of water was lost into the EBB-4 well during drilling of the horizontal well, and this will need to be removed from the near-wellbore area by gas-lifting with the re-compressed gas.

Although continued bad weather has further delayed project completion during January, the installation and tie in of the EBB-5 platform is progressing.

The jacket has been installed offshore and the topsides/deck is currently being mated and welded to the jacket.

Upon completion, the gas injection line and risers will be installed and commissioned, and then the well will be tied into the onshore gas compression system.

The West Titania rig is currently drilling the horizontal production section on the final well in the programme, the EBB-3 well.

Upon completion of drilling, the West Titania drilling rig will be released and the installation of the EBB-3 platform and pipeline hook-ups with the other wells will start, ahead of project completion in March.