Chinese offshore contractor Offshore Oil Engineering Company (COOEC) has started fabrication of offshore facilities for the Marjan incremental project offshore Saudi Arabia following a lengthy delay.

The first steel cut on Tuesday will ensure the completion of an eight-leg tie-in platform with modules weighing 20,000 metric tonnes to be completed for delivery in the first quarter of 2024, two years behind the initial schedule.