End of arbitration: Dispute over Gorgon jetty contract settled

Cimic only picks up a fraction of the A$1.86 billion it was seeking in arbitration proceedings

Centre of dispute: Cimic had been seeking A$1.86 billion in alleged cost blow outs over the construction of the jetty at Chevron's Gorgon LNG project
Centre of dispute: Cimic had been seeking A$1.86 billion in alleged cost blow outs over the construction of the jetty at Chevron's Gorgon LNG projectPhoto: CHEVRON
Published 20 October 2020, 04:00Updated 20 October 2020, 04:00