However, work on other elements of the Dalma development are progressing and sources signalled that it does not necessarily mean a major project slowdown.
Rather, sources close to the tender process told Upstream that the state-owned had cancelled the tender for two offshore jackets required for early drilling because it wants to fine-tune the field’s development plan.
“They (Adnoc) are expected to launch a bigger EPC project next year, once the development plan is reworked,” one source said.
The