Dutch company Heerema installed the 2000 tonne jacket with eight piles using the Thialf heavy lift vessel in 62 metres of water which was followed by the successful lift and setting of the 1400 tonne integrated deck topsides.
“The installation of the Breagh platform marks another significant milestone for the Breagh field development following on from the successful installation of the pipelines to shore earlier in the year,” RWE Dea chief operating officer Ralf to Baben.
“This