Project co-owner Oil Search said in its latest drilling report the joint venture has formally agreed to drill the Antelope-7 appraisal well.

Well pad construction is under way and expected to be completed by the end of August, with the well scheduled to spud in September 2016.

The objective of the well will be to test for reservoir presence and definition on the western flank of the field.

Another