It follows a “record turnaround time” of just four months for integration of topside modules on the vessel by SBM Offshore under an engineering, procurement and construction contract.

That compares with five months for similar integration work on the previous FPSO converted at the yard, Cidade de Marica, that came online in February.

Following sailaway, the new unit will be delivered to Petrobras for work in the Santos basin.