The contract was awarded by Maersk Oil and includes the central processing facility topsides plus two connecting bridges, a wellhead platform topsides and a utilities and living quarters platform topsides.
The facility will be installed at a water depth of 90 meters on the Culzean field, which is a high pressure, high temperature gas and condensate development.
SMOE will provide engineering, procurement, construction and onshore pre-commissioning services while detailed engineering will be performed by a sub-contracting partner, said SMOE's parent company SembCorp Marine.