Production has been shut in at the subsea development since 7 February asa result of the glitch that occurred following the tie-in of the second producingwell on the field, East Rochelle E2.
The addition of the well, which involved taking thealready-producing West Rochelle W1 temporarily offline, had already been put back from December toJanuary because of unfavourable weather conditions before the technical issue.