The $99.5 million contract was awardedby Malaysia's Petronas and relates to a gas treatment facility beingbuilt at the field to treat theassociated gas from the Mishriffoil train and supply it to a power plant at the Garraf field.
Under the contract STX will beresponsible for the EPC and commissioning of the project which isexpected to run for 24 months, with completion scheduled for the endof November 2015.
Production