The unit has been contracted by Brazil's Petrobras for 11 years, with extension options for a further 11 years, for work on the Piranema field off Brazil.

The Piranema FPSO was built using an innovative cylindrical design but was beset by cost overuns and delays.

Sevan earlier said that the unit was $45 million over budget and four to five months behind schedule.