Project operator Woodside said the review should be completed in the third quarter of 2006, and was being done because of “increasing cost pressures”.
To date, about 80% of the project’s approved budget has been committed. In the last three months, the piping pre-fabrication and new workshop contracts were awarded, and a letter of intent was issued for the mechanical construction contract.
In