Indonesian operator Medco Energi is aiming for production start-up in in the first quarter of 2018 from its $800 million Block A gas fields development in Nanggroe Aceh Darussalam, Indonesia.

Medco is targeting a commissioning date for the onshore field ­facilities of December 2017 or January 2018.

Gas should be flowing before the end of March 2018.

However, a Medco source ­cautioned: “We are still finalising issues with our partner”.