The estimated $2 billion central processing facilities (CPF) package involves the construction of two processing trains to dehydrate 300 million cubic feet per day of sour gas, three sulphur recovery trains, each with capacity of 183 tonnes per day, demethanisation facilities using propane refrigeration, a 1.8 million-barrel tank farm, four flares and two natural gas liquids spheres capable of storing 70,000 barrels.
The