The UK independent said last week it has approved development of the Bison, Iguana and Gajah Puteri (BIGP) project on Block A, where it is chasing up to 93 billion cubic feet of gas. First gas is targeted for the third quarter of 2019.

The three-well development will see the Bison and Iguana fields tied back to the Pelikan platform, with the well on the Gajah Puteri field tied back to the Anoa (also known as AGX) platform.