Malaysian state oil company Petronas Carigali has awarded a major new turnkey contract to Malaysia Marine and Heavy Engineering to build a main processing platform for the Bokor phase three redevelopment project.
The 1 billion ringgit ($227 million) contract covers the engineering, procurement, construction, installation and commissioning of the central processing platform, said MMHE.
The first steel cut is expected in the third quarter of 2018 and the project is scheduled to be completed during the second quarter of 2020.