The pipeline replacement project, initially intended to begin in early 2014, was projected to include 465 days of work across BSP’s producing oilfields lasting to the end of 2017.

About 135 days of work were previously scheduled for 2014, but some of this is now expected to spill over to the three remaining years, given earliest mobilisation is likely during the fourth quarter.

The