The G1 project in the Krishna Godavari basin is troubled by three main factors a dispute with main contractor Clough, delays in completing the installation of subsea production components and bad weather.

The Indian upstream giant has targeted a new start-up date of March 2007 compared with the original target of April 2006, but well-placed sources said March 2007 is optimistic.

The