Petroleum Development Oman’s (PDO) Rabab Harweel Integrated Project is ramping up production, with output on stream from six sour gas wells so far, according to project contractor Petrofac, writes Kathrine Schmidt.
The result was achieved two months ahead of schedule, with production set to ramp up further in the coming months.
Petrofac has been executing its contract to provide engineering, procurement, construction management and commissioning support services worth some $1.25