Cheniere Energy is to begin commissioning activities at the fourth train of its Sabine Pass liquefied natural gas export facility in Louisiana.
The US Federal Energy Regulatory Commission last week authorised Cheniere to introduce feed gas into Train 4, which is expected to reach substantial completion in August and start commercial operations in November. Ferc also recently granted permission for commercial activities to start at Sabine Pass Train 3, which had been in the commissioning process.