Dutch contractor SPT Offshore has completed the installation of the wellhead platform for the Ophir field development off Malaysia, writes Eoin O'Cinneide.

SPT used the heavy-lift unit Sea Aaryan to install the jacket, topsides and boat-landing module over a 72-hour period within the past week.

The jacket and module were both installed on 9 April before the topsides was installed on 11 April.