Chevron’s executive vice president for upstream, James Johnson, said the biggest challenge for project execution at present has been “the delays in module delivery from a fabrication yard, which is putting pressure on the schedule. To address the delays, we have expanded to an additional yard and provided increased oversight in the yards. We have seen positive results from these actions and are not anticipating any further delays in the module delivery schedule,” he added.

The